Update on Elm Street Drainage Project (Euclid Extension)

SHARE NOW

McPHERSON, Kan. — City of McPherson Director of Public Works Jeff Woodward shared an update with McPherson Main Street on the Elm Street Drainage project (Euclid Extension) following a progress meeting Monday, March 24.

“All work up to the intersection, west of Main, South side is complete,” Woodward said. “We will open the drive into the parking lot on Friday.”

Crews have started removals on the north side of Euclid (from the alley to Main). The north side is “tentatively” set to be completed in four weeks, but any rain or other unforeseen issues will push the time out.

Woodward added that the alley on the North Side of Euclid, east of Main is also complete and will be opened up on Friday, March 28.